Federal Grant Closeout Checklist: The 120-Day Rule

How to close out a federal grant under 2 CFR 200.344: final reports and payment of all obligations within 120 days of the end of the period of performance (90 days for subrecipients), equipment and supplies, refunds, what happens if you miss it, and what continues after closeout.

Jump to Checklist
Use browser Print to save as PDF

Final reports and payments

Within 120 days after the period of performance ends

Subrecipients

Within 90 days, or earlier if the subaward says so

Keep records

Three years from submitting the final financial report

The short answer

To close out a federal grant, 2 CFR 200.344 gives a recipient 120 days after the period of performance ends to submit every final report and pay all obligations under the award. Subrecipients have 90 days, or less if the subaward says so. Unspent advances must be refunded, equipment and supplies accounted for, and records kept for three years from the date the final financial report is submitted.

Why this matters

When a federal grant ends, the work isn't over. Within 120 days every final report has to be filed and every bill paid. Miss it and the agency closes the award with whatever it has, any overpayment becomes a federal debt, and the failure is recorded in SAM.gov, where agencies look before making future awards. This checklist follows 2 CFR 200.344, the closeout rule, from the months before the end date to the years after.

1

Before the period of performance ends

Closeout goes smoothly when it starts about three months before the end date, not after it.

  • Confirm the end date from the latest amendment, not the original agreement
  • Only costs incurred during the approved period are allowable; the one exception is administrative closeout costs (§ 200.403(h))
  • If you need more time to finish the work, ask about an extension before the end date, not after
  • Ask vendors to invoice for all work done before the end date
  • Remind subrecipients that their final reports and payments are due to you within 90 days, or earlier if your agreement says so (§ 200.344)
  • Inventory the equipment and supplies bought with award funds

Quick check: For each grant ending in the next 90 days, is the end date confirmed and the closeout on someone's calendar?

2

Within 120 days after the end date

This is the core rule. Subrecipients have 90 days, so their deadline comes first.

  • Submit every final report the award requires, financial, performance and any others, within 120 days (§ 200.344)
  • Pay all obligations incurred under the award within the same 120 days (§ 200.344)
  • Draw down any remaining funds you're owed, and promptly refund any advanced funds you didn't spend (§ 200.344)
  • No final indirect cost rate yet? Submit the final financial report anyway, and send a revised one when the rate is final (§ 200.344)
  • Staff time and other costs of closing out are allowable until the final report is due, charged to the final budget period (§ 200.472)
  • If you need more time, ask the agency or pass-through entity for an extension before the deadline; they can approve one when it's justified (§ 200.344)

Red flag: The final financial report is planned for after the last invoices are paid, and the last invoices aren't due until day 110.

3

Equipment and supplies

Property bought with federal funds has to be accounted for at closeout (§ 200.344).

  • Equipment worth $10,000 or less per unit at closeout can be kept, sold or disposed of with no further obligation (§ 200.313)
  • Equipment worth more than $10,000 per unit: ask for disposition instructions; if you keep or sell it, the agency is owed its share (§ 200.313)
  • Unused supplies worth more than $10,000 in total: the agency is owed its share if you keep or sell them (§ 200.314)
  • Keep property and equipment records for three years after final disposition (§ 200.334)

Quick check: Does the equipment list for this grant match what's actually on site?

4

If you miss the deadline

Closeout happens with or without you, and a missed closeout follows your organization.

  • The agency or pass-through entity must close out the award based on whatever information it has (§ 200.344)
  • If you don't submit your final reports, the federal agency must report the failure in SAM.gov, where every agency checks before making future awards (§ 200.344)
  • Any federal money paid to you beyond what you're entitled to becomes a debt to the federal government (§ 200.346)
  • Agencies aim to finish all closeout actions within one year after the end of the period of performance (§ 200.344)

Red flag: An award ended more than 120 days ago and no one can say whether the final reports went in.

5

After closeout

Closeout ends the reporting, not your responsibilities.

  • The agency can still disallow costs and recover funds after a later audit or review, within the record retention period (§ 200.345)
  • Audit, property and record-keeping duties continue after closeout (§ 200.345)
  • Keep all award records for three years from the date you submit the final financial report (§ 200.334)
  • Keep them longer if litigation, a claim or an audit started before the three years ran out, or if you're told in writing to extend (§ 200.334)
  • Return refunds, corrections and other credits that arrive after closeout (§ 200.345)

Quick check: Does each closed grant's file record the final report date and the date its records can be destroyed?

Signs closeout will be a scramble

If several of these are true for a grant ending soon, start closeout now.

  • The end date in your records doesn't match the latest amendment
  • Vendors and subrecipients haven't been told when to invoice
  • No one owns the final financial and performance reports
  • Equipment bought with the grant hasn't been inventoried
  • Advanced funds may exceed what was actually spent
  • The award's records are spread across several people's files
  • Past awards were never confirmed as closed

Self-score

Give yourself 1 point for every statement you can honestly say is true.

  • End dates are confirmed from the latest amendments
  • Closeout starts 90 days before each end date
  • Subrecipients know their 90-day deadline
  • Final reports and payments are scheduled within 120 days
  • Equipment and supplies are inventoried and dispositioned
  • Unspent advances are refunded
  • Each closed grant has a record-retention date
  • Past awards are confirmed closed

7 to 8: Strong foundation

4 to 6: Some gaps, manageable if addressed now

0 to 3: High risk of preventable problems

Next step

Want closeout on the calendar from the day the grant starts?

GrantGuard reads the agreement, puts the end date and the 120-day closeout deadlines on your calendar, reminds the right people ahead of time, and keeps the final reports and backup with the requirements they satisfy.

Start Free 30-Day Trial Book a Demo
Print this page to save as PDF

Related guides

Sources

Checked against the official text on October 26, 2026: 2 CFR 200 as published in the eCFR on October 22, 2026 (last amended October 1, 2024). Your award terms may set different dates.

  1. eCFR: 2 CFR 200.344, Closeout — 120 and 90 days, refunds, property, one-year target, and reporting failures in SAM.gov.
  2. eCFR: 2 CFR 200.345, Post-closeout adjustments and continuing responsibilities — Disallowances, refunds, audit, property and records after closeout.
  3. eCFR: 2 CFR 200.472, Termination and standard closeout costs — Administrative closeout costs are allowable until the final report is due.
  4. eCFR: 2 CFR 200.334, Record retention requirements — Three years from the final financial report, with the exceptions.
  5. eCFR: 2 CFR 200.313 and 200.314, Equipment and supplies — The $10,000 disposition thresholds.